A Professor of Forensic Accounting has told a Rivers State High Court in Port Harcourt how the Nigeria Liquefied Natural Gas Limited (NLNG) came about owing one of its indigenous contractors, Macobarb International Limited the sum of N5.074 Billion.
The expert, Professor Yohanna Jugu, Senior Partner at W. J. Jugu & Co, Jos, Plateau State told the presiding judge in Suit No: PHC/2013/CS/2022, Justice Chinwendu Nwogu that he (the expert) worked out the indebtedness from the contract document and performance history of number: B130142PPI (Access Control Contract) awarded by the NLNG to Macobarb in 2014.
L-R Managing Director, Nigeria Liquefied Natural Gas Limited, Philip Mshelbila; Managing Director, Macobarb International, Shedrach Ogboru;
He told the court that he relied on Sections 2, 7, 8 & 9 of the contract to calculate the liabilities creditable to Macobarb by the NLNG, noting that Section 9 is the Macobarb Bill of Quantities.
In the said suit, A.J. Okanje represented the claimant, Macobarb International Limited, while Prof Bayo Adaralegbe stood in for the defendant, Nigeria Liquefied Natural Gas Limited (NLNG).
He further agreed with the defence counsel who read out the content of Section 7, subsections: 5.11, 12.4, 13.2 thus: “If, by reason of any failure or inability of the engineer, the Company’s Representative and/or the Company to issue within a time reasonable in all the circumstances any drawing, instruction, approval or the like for which notice has been given by the Contractor, the Contractor suffers delay and/or incurs costs, then the time for the execution of the works shall be extended accordingly and the amount of such costs shall be added to the Contract Sum”.
He also agreed when the lead defence counsel, Prof Mayo Adaralegbe, read out Subsection 12.4 to show that any inferior materials or items supplied by the contractor shall be at the contractor’s account.
“Such costs shall include any standing time for pending delivery of acceptable Plant/equipment/tools/vehicles. Where Contractor’s programme for the Work is delayed as a result, the Contractor shall provide additional resources to recover the time lost so as not to delay the stage completion date/s for the works”.
This was interpreted to mean that whichever side caused delay of job shall pay the added cost. The witness said this was the provision he relied on to calculate cost of delays caused by the NLNG.
The statement he submitted and affirmed in court indicated that the only standing time not provided for in the engineering, procurement and construction (EPC) contract is on engineering design because, he said, it is elementary in design.
The defence counsel, Prof. Adaralegbe drilled the witness for hours and asked him (the expert witness) if he was aware that the contract was terminated sometime in November 2015.
He answered that he saw document like that but that when he asked his client, Macobarb, they informed him that the termination was a breach in the sense that the ‘Contract Holder’ was the one to have terminated the contract.
Prof Adaralegbe pinned the witness to admit that the total sum of the contract was N95m and asked the witness how he calculated the debt (if any) at over N5 Billion, to which he answered that it was for job done that was not paid for, and the breaches that occurred from the contract.
He rather told the court that if he was mandated to calculate the time value of money arising from the contract crisis, that he would get another N800m to be compensated.
The fireworks raged for hours but Justice Nwogu reminded the two professors that they can profess all they knew as professors but that he will dwell only on the law.
The hearing continues on October 29, 2024, when the Managing Director of Macobarb, Shedrack Ogboru, would be led to mount the witness box by his latest lead counsel, A. J. Okanje, to tell the court what happened in the controversial contract.
Macobarb International Limited, an indigenous contractor had dragged the NLNG to court claiming over N1 Billion (now amended to N5.074Billion) for alleged breaches to a contract (B130142PPI, Access Control) in the NLNG plant area with three years’ duration.
The suit said the contract provided that Macobarb be paid bit by bit progressively based on the value of verified work done.
Macobarb in its claims said the contract also forbade delay of any kind in the project and provided for penalty on whoever caused the delay. It also provided for alert system should anything want to cause a delay.
Macobarb said it activated the alert clauses when payment delays began to happen but that nothing was done to rectify the delays until the contract was terminated